Projects
Confidential Client1
Where:
Multiple locations in the US
What:
Multiple Large Spiral Freezer Replacements including process and packaging improvements in an operating food plant.
Average Cost:
10,000,000
Scope
Provide Construction Project Management to plan and execute the removal of existing aged and abused spiral freezers that have multiple food safety issues. Redirect and maintain the GMP of portion of the plant still in operation. Upgrade the structural, civil, sanitary design, utility, fire suppression and ammonia systems to support the new freezers, process upgrades and packaging upgrades.
Our experts’ experience runs deep with a combine 75 years of experience with the company founders alone. The unique environment of each facility takes special attention and care when planning and executing to create the proper environment while under construction. Here are some examples of the type of projects Thermline Inc. is capable of executing.
Confidential Client3
Where:
Grand Rapids, Michigan
What:
Facility upgrade to accommodate a new cereal manufacturing line.
Scope
Facility and utility upgrades, installation of full process from receiving of raw goods to shipping of packaged final product. Process included, Super sack dumpers, conveyors, coating drums, multiple slurry processes for coating of product, dryers and coolers, bucket elevators, shaker conveyors, scales, baggers, cartner, labeler, case packer, and associated controls. Facility up grades included full GMP environment which involved proper drains, flooring material, IMP walls and walk on ceiling sanitary fixtures and sanitary installation of utility support items.
Scope
Provide Construction Project Management to plan and execute the removal of existing aged and abused dehydration drying ovens with multiple food safety issues. Redirect and maintain the GMP of portion of the plant still in operation. Installed new High Efficiency dehydration dryers. New Reclamation system for process by-product. Upgrades of utilities, fire suppression and plant sanitation.
Scope
Provide Construction Project Management to plan and execute 25,000 SF Plant addition with all utility upgrades and complete New packaging line expansion for partnering manufacturing clients. Installed new material handling line delivery system to product division scales, Complete system included Baggers, Cartoners, Case Packers and Palletizer systems including all conveyance.
Scope
70,000 SF Milk plant expansion including a 120’ tall AS/RS cooler. Insulated panels and specialty doors
Scope
40,000 SF Facility expansion. Design build insulated panels, specialty doors and energy efficient refrigeration
Scope
160,000 SF new distribution facility. Design build insulated panels, specialty doors and energy efficient refrigeration